Pollini Swale Restoration Quote – March 12, 2024

Job will include:
(1) excavation of trench to maintain a depth of 2’ below road and a 3’ width at bottom.
(2) apply 6/8” erosion stone to both sides an bottom. Compact stone into both sides and bottom.
(3) all materials Will be used at bottom of hill to increase the size and integrity existing berm. Finish product will be placed over berm.
(4) outfall into woods at bottom will be reshaped and stone applied.
(5) job duration will be approximately 3 Days.
BREAKDOWN

Mini Excavator @ $1,100/day
Skid Steer @ $1,000/ day
Truck time based on 10hrs @ 140/ hrs- $1400
(5) 25 ton loads/16 yds @ $576 – $2880
Labor: 10hrs @ $80 – $800

TOTAL: $11,380
Quote price of $11,000

Side note: any work done on private properties will be discussed with contractor and billed separately.

Thank you, John Pollini-Pollini Bros Construction (603) 569-1652